he project is winding down for the week and the last piece of stormwater pipe on East Main Street has been installed! (see picture)
Monday the construction crews will continue curb/sidewalk restoration and begin trench restoration. Trench restoration involves leveling and paving the areas of road that were dug for the infrastructure installation. Final paving of East Main Street will not take place until the South Decatur Street portion of the project is also complete. Construction should be completed on East Main Street the week of May 18th. If all goes as planned, the East Main Street detour will end just before Memorial Day weekend. The South Decatur Street detour and construction will begin just after Memorial Day.
A Strasburg Borough staff member will be onsite at all times during the project. If you have any questions, concerns, or complaints, please contact the Borough Office at 717-687-7732 or e-mail Borough Manager, Steve Echternach, at echterns@strasburgboro.org.
Thank you for your cooperation and patience during this project!