East Main Street/South Decatur Street/Shenk Avenue Stormwater Project Update #16
Construction continues and the contractor is still on schedule. They will continue with curb and sidewalk restoration in the next 2 weeks. They have started some paving of the cross sections and the main part of the trench restoration will be completed during the week of May 18th.
The East Main Street portion of the work is anticipated to be completed on Thursday, May 21st. The East Main Street detour will come down on May 22nd and the South Decatur Street detour will begin on May 26th.
A Strasburg Borough staff member will be onsite at all times during the project. If you have any questions, concerns, or complaints, please contact the Borough Office at 717-687-7732 or e-mail Borough Manager, Steve Echternach, at echterns@strasburgboro.org.
Thank you for your continued patience and understanding during this project!